  1. Q.1

    A can complete a work in 10 days and B can complete the same work in 15 days. If they work together, in how many days will they finish it?

    Show answer

    Answer: 6 days

    Solution:

    1. A’s rate = 1/10, B’s rate = 1/15 per day.
    2. Combined rate = 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6 of the work per day.
    3. Time to finish together = 1 ÷ (1/6) = 6 days.

    Report this question

  2. Q.2

    12 men can build a wall in 15 days. How many men, working at the same rate, are needed to build it in 10 days?

    Show answer

    Answer: 18 men

    Solution:

    1. For the same total work, Men × Days stays constant: 12 × 15 = 180.
    2. For 10 days: Men = 180 / 10
    3. = 18 men

    Report this question

  3. Q.3

    A and B together can complete a work in 12 days. A alone can complete it in 20 days. In how many days can B alone complete the work?

    Show answer

    Answer: 30 days

    Solution:

    1. Combined rate (A + B) = 1/12. A’s rate = 1/20.
    2. B’s rate = 1/12 − 1/20 = 5/60 − 3/60 = 2/60 = 1/30 of the work per day.
    3. B’s time alone = 1 ÷ (1/30) = 30 days.

    Report this question

  4. Q.4

    A can finish a work in 10 days and B in 15 days. They work on alternate days, starting with A. In how many days will the work finish?

    Show answer

    Answer: 12 days

    Solution:

    1. A's rate = 1/10, B's rate = 1/15. In each 2-day cycle (one day A, one day B), work done = 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6.
    2. After 6 cycles (12 days), work done = 6 × 1/6 = 1 — exactly the whole job, with no leftover day to analyse.
    3. So the work finishes in exactly 12 days.

    Report this question

  5. Q.5

    A can complete a piece of work in 12 days. What fraction of the work does he complete in 4 days?

    Show answer

    Answer: 1/3 of the work

    Solution:

    1. A’s rate = 1/12 of the work per day.
    2. Work done in 4 days = 4 × (1/12) = 4/12
    3. = 1/3

    Report this question

  6. Q.6

    A can do a piece of work in 20 days. B is 25% more efficient than A. Find the number of days B alone takes to complete the same work.

    Show answer

    Answer: 16 days

    Solution:

    1. "25% more efficient" means B’s work rate is 1.25 times A’s rate.
    2. Since time is inversely proportional to rate, B’s time = A’s time ÷ 1.25 = 20 ÷ 1.25
    3. = 16 days

    Report this question

  7. Q.7

    A and B together can complete a work in 12 days. They work together for 4 days, after which A leaves, and B alone completes the remaining work in 16 more days. In how many days could B alone have completed the entire work?

    Show answer

    Answer: 24 days

    Solution:

    1. Combined rate = 1/12. Work done in the first 4 days = 4 × 1/12 = 1/3.
    2. Remaining work = 1 − 1/3 = 2/3, and B alone finishes this in 16 days, so B's rate = (2/3) / 16 = 1/24.
    3. B alone would take 1 ÷ (1/24) = 24 days for the entire work.

    Report this question

  8. Q.8

    A can finish a work in 8 days and B in 12 days. They work on alternate days, starting with A. In how many days will the work be completed?

    Show answer

    Answer: 9.5 days. 4 full cycles (8 days) complete 5/6 of the work; day 9 (A) adds 1/8, leaving 1/24; B finishes that 1/24 in half a day at B's rate of 1/12 per day.

    Report this question

  9. Q.9

    A can complete a work in 6 days and B can complete the same work in 12 days. Working together, how many days will they take?

    Show answer

    Answer: 4 days. Combined rate = 1/6 + 1/12 = 1/4.

    Report this question

  10. Q.10

    A and B can together finish a work in 15 days. They work together for 5 days, then A leaves and B alone finishes the remaining work in 20 more days. Find how long B alone would take for the entire work.

    Show answer

    Answer: 30 days. Work done together in 5 days = 1/3; remaining 2/3 takes B 20 days, so B's rate = 1/30.

    Report this question

  11. Q.11

    A and B together can complete a work in 15 days. B alone can complete it in 25 days. In how many days can A alone complete the work?

    Show answer

    Answer: 37.5 days. A's rate = 1/15 − 1/25 = 2/75; time = 75/2.

    Report this question

  12. Q.12

    15 men can complete a job in 8 days. How many men, at the same rate, are needed to complete it in 6 days?

    Show answer

    Answer: 20 men. Men × Days = 120 (constant); 120/6 = 20.

    Report this question

  13. Q.13

    A can complete a work in 8 days. What fraction of the work does he complete in 3 days?

    Show answer

    Answer: 3/8 of the work.

    Report this question

  14. Q.14

    A can do a work in 18 days and B in 24 days. They work together for 8 days. What fraction of the work remains?

    Show answer

    Answer: 2/9. Combined rate = 1/18 + 1/24 = 7/72; work done in 8 days = 56/72 = 7/9; remaining = 2/9.

    Report this question